UAE becomes first Arab country to develop nuclear energy plant to generate safe, clean electricity
ABU DHABI: The Emirates Nuclear Energy Corporation (ENEC) today announced that its operating and maintenance subsidiary, Nawah Energy Company (Nawah) has successfully started up Unit 1 of the Barakah Nuclear Energy Plant, located in Al Dhafrah Region of Abu Dhabi.
This step is the most historic milestone to date in the delivery of the UAE Peaceful Nuclear Energy Programme, as part of the process towards generating clean electricity for the Nation for at least the next 60 years, the United Arab Emirates (UAE) news agency WAM reported.
Since receipt of the operating license from the Federal Authority for Nuclear Regulations (FANR) in February 2020, and the completion of fuel assembly loading in March 2020, Nawah, the Joint Venture nuclear operations and maintenance subsidiary of ENEC and the Korea Electric Power Corporation (KEPCO) has been safely progressing through a comprehensive testing programme, prior to successfully completing the start-up of the first nuclear energy reactor of the Barakah plant.
The start-up of Unit 1 marks the first time that the reactor safely produces heat that is used to create steam, turning a turbine to generate electricity.
Nawah’s qualified and licensed team of nuclear operators focus on safely controlling the process and controlling the power output of the reactor.
After several weeks and conducting numerous safety tests, Unit 1 will be ready to connect to the UAE’s electricity grid, delivering the first megawatts of clean electricity to the homes and businesses of the Nation.
Testing has been undertaken with the continued oversight of the UAE’s independent nuclear regulator, FANR, and follows the World Association of Nuclear Operator’s (WANO), completion of a Pre Start-up Review (PSUR), in January 2020, prior to receipt of the operating license, which ensures Unit 1 is aligned with international best practice in the nuclear energy industry.
“Today is a truly historic moment for the UAE. It is the culmination of more than a decade of vision, strategic planning and robust program management,” Mohamed Ibrahim Al Hammadi, ENEC Chief Executive Officer, said.
“Despite the recent global challenges, our team has demonstrated outstanding resilience and commitment to the safe delivery of Unit 1. We are now another step closer to achieving our goal of supplying up to a quarter of our Nation’s electricity needs and powering its future growth with safe, reliable, and emissions-free electricity.”
“Through the realization of the vision of our Leadership, the Barakah Nuclear Energy Plant has become an engine of growth for the nation, he added.
“It will deliver 25 percent of the UAE’s electricity with zero carbon emissions while also supporting economic diversification by creating thousands of high-value jobs through the establishment of a sustainable local nuclear energy industry and supply chain.
We are grateful to the Leadership for their continuous support in making this remarkable achievement happen, along with the support of our UAE stakeholders and Korean partners, and congratulate everyone involved in the Programme on this landmark occasion.”
Once the unit is connected to the grid, the nuclear operators will continue with a process of gradually raising the power levels, known as Power Ascension Testing (PAT).
Throughout, the systems of Unit 1 are continuously monitored and tested as the unit proceeds towards full electricity production in line with all regulatory requirements and the highest international standards of safety, quality and security. Once the process is completed over the course of a number of months, the plant will deliver abundant baseload electricity at full capacity to power the growth and prosperity of the UAE for decades to come.
“The start-up of Unit 1 is a significant milestone for Nawah Energy Company as we fulfill our mandate to operate and maintain the plant in accordance with the highest international standards of safety and quality,” Nawah Chief Executive Officer Ali Al Hammadi said.
“The dedication of our people as well as our close collaboration with our Korean partners and cooperation with numerous international expert organisations has enabled this accomplishment. This reflects our commitment to upholding the highest safety, quality and operational transparency standards throughout the entire commissioning and startup process by leveraging the expertise of the global nuclear industry.
“I am especially proud of our talented UAE National engineers and nuclear professionals who contributed to the construction of Unit 1, as well as the UAE National Senior Reactor Operators and Reactor Operators who have been certified to safely operate the plant, alongside our international experts, to ensure the safe and sustainable operations of the unit for decades to come.”
The UAE is the first country in the Arab World, and the 33rd globally, to develop a nuclear energy plant to generate safe, clean, and reliable baseload electricity.
The Barakah plant is significantly contributing to the UAE’s efforts to move towards the electrification of its energy sector, and the decarbonisation of electricity production.
When fully operational, the plant will produce 5.6 gigawatts of electricity while preventing the release of more than 21 million tons of carbon emissions every year, equivalent to the removal of 3.2 million cars from the Nation’s roads annually.
Since the UAE Peaceful Nuclear Energy Programme was launched in 2009, ENEC has worked closely with international nuclear bodies, including the International Atomic Energy Agency (IAEA) and WANO, in line with the robust regulatory framework of FANR.
To date, more than 255 inspections have been undertaken by FANR to ensure the Barakah plant and its people and processes meet the highest standards of nuclear quality and safety. These national reviews have been supported by more than 40 assessments and peer reviews by IAEA and WANO.
ENEC recently announced the construction completion of Unit 2, with operational readiness preparations now underway by Nawah.
Construction of Units 3 and 4 of the Barakah Nuclear Energy Plant is in the final stages, with the overall construction completion of the four units now standing at 94 percent.